CCPP GUD1NEU MUNICH SOUTH
Germany

 

Stadtwerke München (SWM) is replacing the existing 850 MW GuD1alt plant with a new 435 MW GuD1neu plant. As before, the new plant will be used to generate electricity and district heating, with the new plant achieving higher efficiencies and improved flexibility. The new plant will be installed in the existing building of the old high-pressure steam boiler plant. This will involve significant changes to the support structures as well as roofs and facades of the existing buildings. After commissioning of the new plant, the old CCGT plant will be decommissioned.

On behalf of SWM, convex ZT GmbH is responsible for design coordination, schedule monitoring, execution design and tender preparation as part of the civil- and structural design team.

Client:
Stadtwerke München Services GmbH, Germany
General designer:
Uniper SE
Capacity:
435 MW
Start of construction:
Autumn 2020
Operation:
Spring 2022

-
Digital twin:
convex ZT GmbH